November Update:

  • The excavations for all three foundations have been dug.
  • The surfaces of the excavation bases have been inspected, tested, and prepared for the blinding.
  • The drainage and conduits have been installed.
  • The blinding has been poured, the steel reinforcing delivered and pin baskets assembled.
  • The steel reinforcement cages on all three sites are nearly complete.
Sorry, no public access. Laying the builders black plastic. Rolling the soil replacement. Pouring the blinding. Delivering reinforcing steel for two turbine foundations. Basket weaving begins.