November Update:
-
The excavations for all three foundations have been dug.
-
The surfaces of the excavation bases have been inspected, tested, and prepared for the blinding.
-
The drainage and conduits have been installed.
-
The blinding has been poured, the steel reinforcing delivered and pin baskets assembled.
-
The steel reinforcement cages on all three sites are nearly complete. |
|